CHEMICALS UNLOADING AND STORAGE FOR WATER TREATMENT PLANT

Execution Time from: 05/1997
to: 05/1998
Execution Stage
Documentation for Building Permit
Detail Design
Lump Sum Turn Key
Client ECK Generating s.r.o., Kladno
 

The project solved an unacceptable state of the unloading of chemicals for chemical treatment of water from rail tank cars and its storage.

A new unloading station for chemicals from rail tank cars was constructed, a new storage facility with a total capacity of 2 x 80 m3 NaOH, 2 x 80 m3 HCl a 2 x 40 m3 Fe2(SO4)3 and piping connections from the unloading station to diluted tanks in WTP were constructed.