Execution Time |
from: 11/2022
to: 07/2023 |
Execution Stage |
Basic Design
Documentation for Building Permit
Documentation for Planning Permit
Detail Design
Lump Sum Turn Key
|
Client | BorsodChem MCHZ, s.r.o. |
The aim of this project was the complete engineering and implementation of optimization of the existing cyclohexylamine (CHA) and dicyclohexylamine (DCHA) production plant for DCHA production only with the target of intensifying production up to the level of 10 kt/year.