Execution Time |
from: 2012
to: 2013 |
Execution Stage |
Documentation for Building Permit
Detail Design
|
Client | RWE Gas Storage, s. r. o. |
The project solved relocation of control rooms and instrumentation control rooms to newly reconstructed buildings further from the technology.
Relocation of the control rooms was one of the conclusions of the safety study and the HAZOP.
Civil design of the relocation of the control rooms was prepared including the interior design – the control room, the room for operators and sanitary facilities. The project further included FDS, GDS and an upgrade of the control system.