BUTADIENE REVAMP

Investment Costs CZK
Execution Time from: 10/2019
to: 05/2020
Execution Stage
Detail Design
Lump Sum Turn Key
Client Butadien Kralupy a.s.
 

The aim of this project was to modify and optimize the technological equipment of the existing Butadiene unit to process the raw material with a higher concentration of ethyl a vinylacetylene.

For this purpose, it was neccessary to replace the packing and internals in one column, to modify a heat exchanger, to replace a part of field instrumentation and some piping connections.