Execution Time |
from: 08/2005
to: 11/2007 |
Execution Stage |
Lump Sum Turn Key
|
Client | CHEMOPETROL, a.s. |
Design and execution of new high pressure steam piping.
The replacement was made during a shutdown – installation and reconnection of prefabricated parts.
Process Intecha.