TANK RECONNECTION

Execution Time from: 04/2016
to: 06/2016
Execution Stage
Lump Sum Turn Key
Client UNIPETROL RPA, s.r.o.
 

This project was carried out in the storage of feed liquids for cracking furnaces at the ethylene plant in UNIPETROL RPA, s r.o. area.

The aim of this project was to ensure the operation of the ethylene unit and to secure the continuous supply of raw feed materials for cracking furnaces and fuel for boiler house during the ethylene plant start-up and also during the time of the virgin naphta tank reconstruction.