Execution Time |
from: 03/2009
to: 10/2009 |
Execution Stage |
Lump Sum Turn Key
|
Client | SYNTHOS Kralupy a.s. |
The main objective of the project was to increase safety in the Storage of liquified gases (SKP) during loading and unloading of rail tank cars by liquified hydrocarbon gases.
To achieve this aim, a new railway siding with roofing was built for six unloading and one loading posts, equipped by a rope shunting device and a scales. A new facility with two buffer tanks and four barrel pumps was built for unloading. The existing pump station for loading was expanded and new pumps were installed.