RECONSTRUCTION OF GASOLINE REFINING UNIT

Execution Time from: 01/2000
to: 04/2001
Execution Stage
Detail Design
Engineering, Procurement, Construction
Client ČESKÁ RAFINÉRSKÁ, a.s.
 

Reconstruction included modification of the existing storage tanks, procurement of new pumps and piping connections in the scope of the mechanical part of the project. Intecha was also responsible for all the civil, electrical and instrumentation parts of the project.