RECONSTRUCTION OF UNLOADING RAILWAY STATION

Execution Time from: 01/2000
to: 05/2001
Execution Stage
Detail Design
Engineering, Procurement, Construction
Client ČESKÁ RAFINÉRSKÁ, a.s.
 

Intecha finalized the concept of the process with giving the consequent functional guarantee of the entire system.

Reconstruction in the mechanical part included namely installation of new unloading arms on railway station and complete reconstruction of the pump station including piping connections.

Besides the mechanical part of the project, all the necessary and related activities in the civil, electrical and instrumentation parts were also executed.