THE FB-103 TANK INSTALLATION AT ETHYLENE UNIT

Execution Time from: 09/2017
to: 02/2018
Execution Stage
Lump Sum Turn Key
Client UNIPETROL RPA, s.r.o.
 

Demolition of original Tank FB-103 was executed due to the fact that the tank was in a significantly corroded state and it could not be used to storage of hydrocarbons. It was replaced by a new tank intended as a feed tank for primary naphtha to pyrolysis furnaces.

New tank FB-103 was made of stainless steel while the original one was made of carbon steel.

The project of new Tank FB-103 with a volume of 200 m3 included especially design, manufacturing, it’s installation on existing repaired foundation, reassembly of original/new instrumentation, installation of Fire fighting equipment, delivery and assembly of Steel structure and reassembly of original piping connected to the tank.